Monday, October 21, 2013

October 21, 2013 Pre-drywall

Insulation going up. We had a pre-drywall meeting today. We walked through the home with our project manager. There were a couple things that needed fixed with the electrical. We had ordered 3 extra outlets in the garage that were not there yet. They are being added. There was also an extra outlet upstairs in our bedroom in an odd place. They are fixing that and flipping it to laundry room. We will get to keep the additional outlet and it is being made more useful by flipping it to laundry room. We got our closing date, we take possession on Dec 20th closing, Dec 21st - moving party!




Friday, October 18, 2013

October 18, 2013 Electrical done!

This week they worked on electrical and dug a trench for the sump drainage. We have our pre-drywall meeting arranged for Monday. Things are moving smoothly and Im already in love with the house!













Sunday, October 13, 2013

October 13, 2013 Hvac, plumbing and porches Oh My!

I got to walk around inside and took some pictures of the HVAC, Plumbing etc.





Front door

Garage door














Master bathtub


Fireplace (gas)




Basement bathroom








Family Bathroom

Bedrooms 1 and 2

Bedroom 3

Master bedroom and bathroom

Master Bath

My walk in closet ( looking into bedroom 1 )

Garage Side door

Patio doors off of morning room


Current view from the front of the house the roof is on and the perimeters around windows have been sealed


Tuesday, October 8, 2013

October 7, 2013 - Cement

Cement floor and outdoor steps poured. They are also working on HVAC and plumbing. Due to wet cement I could only get outside pictures today.